The Ramco Cements has commenced the work to expand its Haridaspur cement grinding unit capacity from 0.90 million tpa to 1.80 million tpa (Line-II) by installating an additional cement mill of 165 tph capacity in Jajpur district of Odisha.
The Line-II will spread over an area of 24.55 acres of land parcel.
In May 2022, Ramco Cements received environment clearance for the project. The board of directors of the company had already approved the project.
As per the information shared with Projects Today, the company has already roped in, contractor and machinery supplier for the project and has started the work on the same.
The company expects to complete the work on the project by Q1/FY2025.